Analysis of price and ceiling work material

Analysis of unit price ceiling is calculated in units m2, while the ceiling is calculated in units lis m1.

Examples of calculation of the volume of work ceiling
a bedroom measuring 3 mx 3 m will be installed ceiling motif multiplex measuring 120 x 120 cm, what is the number of multiplex, lis ceiling and ceiling frame that must be purchased or reserved?

to analyze the employment ceiling price for the room, we first calculate the area of the room is:

L = 3 m × 3 m = 9 m2

our next multiplex analysis needs to be provided.


calculate the multiplex needs a ceiling material
1 sheet multiplex on the market measuring 1.2 mx 2.4 m. whereas we would wear a size of 1.2 m x 1.2 m. 1 multriplek intact means will we cut it into two parts.
room width = 9 m2
spacious 1 motif multriplek size of 1.2 mx 1.2 m = 1.44 m2
hence the need multriplek = 9 m2: 1.44 m2 = 6.25 fruit size of 1.2 mx 1.2 m
murtiplek means the amount to be purchased (the size of 1.2 mx 2.4 m) is a = 6.25: 2 = 3.125 rounded pieces of fruit 3.5
when the ceiling workmanship possible risk of damage, disability or the remaining unused deduction limit, so as we add security numbers 1 sheet in the purchase of 3.5 + 1 = 4.5 sheet. and if not allowed to buy multriplek half sheet then we bought a number of 4 sheets multriplek.

Calculating the need for timber frame ceiling
wood frame required amount can be analyzed as follows
room size 3m x 3m then the wood frame is attached to the walls along the x4 3m bh = 12 m1
1 motif size limit is 1.2 mx 1.2 m, then the need for timber frame ceiling is 3 x 4 pcs = 12 m1
wood frame hanger 5 pcs x 1 m = 5m
then the total number of timber frame ceiling requirement is 12 m + 2 m + 12 m = 36 m1

calculate needs ceiling trim
lis ceiling we put on the meeting between the edge of the ceiling to the walls, the ceiling trim required is equal to 3 x 4 pcs = 12 m1
calculate needs paint ceiling
if we add the finishing paint a ceiling, the ceiling paint needs to calculate the area of the room that we need a 3 mx 3 m = 9 m2 ceiling paint job.
for the needs of power and auxiliary materials such as nails, threads etc. can be adjusted in the field, and later can memperkiakan needs auxiliary materials such as reference for subsequent ceiling work.
after we know the total volume of labor, materials or materials course, we've estimated that a fee that will be needed by multiplying the volume of the material at the market price.